Rule 4
Applying for Power Generation Survey Permit
A person or an organization wishing to conduct a survey of power generation should submit the following details related to the proposed power generation project to the Director General:
(a) Map of the project site (which should clearly show the preliminary map of the proposed power house, dam, reservoir, canal, tunnel, sub-station, transmission line, distribution area etc. and villages, towns, historical places, roads etc. within the project area) ),
(b) the area of the water source to be surveyed and the quantity of water to be used,
(c) Estimated cost and total duration (including survey and construction) of project completion,
(d) Estimates of total connected capacity and annual production of the project,
(e) the type of fuel to be used and the method of its supply in case of generating electricity from means other than water,
(f) Other necessary things.
(b) the area of the water source to be surveyed and the quantity of water to be used,
(c) Estimated cost and total duration (including survey and construction) of project completion,
(d) Estimates of total connected capacity and annual production of the project,
(e) the type of fuel to be used and the method of its supply in case of generating electricity from means other than water,
(f) Other necessary things.