You are viewing the translated version of स्पष्टीकरण माग गर्ने अधिकार.

Rule 41
Right to demand an explanation
: During the inspection and investigation, if the contractor does not do the work required to be done according to the law, these regulations and the petroleum contract or does any irregular work, the inspector can demand an explanation from the contractor and the contractor must give a written explanation within the time specified by the inspector.